Lundin Mining says Caserones mine in Chile faces 2-3 week restart delay after storm damages powerline towers

Lundin Mining says Caserones mine in Chile faces 2-3 week restart delay after storm damages powerline towers

ReutersReuters2026/07/27 06:07
By:Reuters
  • Lundin Mining flagged a storm-related outage at its Caserones mine in Chile, with power down since July 18 due to damaged transmission towers.
  • Repairs are under way; full power restoration and a gradual restart are expected to take about two to three weeks.
  • Backup generators are supporting critical infrastructure while access roads reopen and crews rotate.
  • Candelaria mining briefly slowed by heavy rain; the mill kept running on stockpiles and mining has returned to full capacity.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Lundin Mining Corporation published the original content used to generate this news brief on July 26, 2026, and is solely responsible for the information contained therein.

0
0

Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.

Understand the market, then trade.
Bitget offers one-stop trading for cryptocurrencies, stocks, and gold.
Trade now!