Fortuna Mining approves USD 109 million expansion of Seguela gold mine in Ivory Coast
Reuters2026/07/30 00:57- Fortuna Mining set a 30% expansion of the Séguéla gold mine processing plant in Côte d’Ivoire, lifting capacity to 2.3 Mtpa from 1.75 Mtpa.
- Average gold recovery targeted at 94.5%; plan supports average annual production above 200,000 ounces over the next decade.
- Estimated construction capital of USD 109 million; projected payback period about 2.5 years.
- Funding planned from operating cash flow; liquidity stood near USD 800 million at end-Q1 2026.
- Construction expected to start in H2 2026; Sunbird underground mining slated for Q2 2027; ramp-up to full 2.3 Mtpa targeted in H2 2028.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Storage Giant Offers Huge Bonuses Again: Micron Awards Up to 68 Months’ Bonus
Micron Technology has announced record-breaking bonuses for its employees in Taiwan, ranging from 35 to 68 months’ salary, with a minimum cash compensation of 1.7 million New Taiwan dollars. However, the Taoyuan union, representing about two-thirds of Micron’s workers in Taiwan, has refused to accept the offer, insisting that 15% of operating profits be included in the bonus distribution and maintaining the threat of a strike.

Dogecoin ETF Closure Sets October Exit for Bitwise BWOW Holders