Hock Lian Seng explains FY2026 interim miss after project costs rise, claims talks stall
Reuters2026/08/05 09:23- Hock Lian Seng issued a clarification on why guidance given in April and May diverged from its 1H ended June 30, 2026 results.
- Earlier guidance pointed to civil engineering revenue comparable to FY2025, with management stating all ongoing projects remained profitable.
- The group cited higher-than-anticipated costs tied to design enhancements, enabling works, inflation, transport, subcontractors, steel, concrete, manpower.
- Claims discussions with project owners stayed inconclusive by early July, prompting a contract margin cut and an onerous contract provision.
- Aviation Park Station was about 70% complete; Serangoon North Station about 46%; price fluctuation clauses did not fully offset added scope costs.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Japanese Yen: Carry unwind supports gains against US Dollar - ING
Wall Street Brings the French Election to the Betting Table! Goldman Sachs and Deutsche Bank Package French Bank Debt, AT1 Bonds Become New Chips
Wall Street is turning next year's French presidential election into an investment strategy for traders, regardless of their expectations for the election outcome.

ABM Q3 FY26 GAAP net income rises 19% to $49.7 million; revenue climbs 4.2% to $2.3 billion
Kalshi's $400 million-plus monthly commodity trade volume outpaces early crypto growth