Newcore Gold files NI 43-101 pre-feasibility study technical report for Enchi gold project in Ghana
Reuters2026/08/07 21:06- Newcore filed an NI 43-101 technical report supporting a pre-feasibility study for the Enchi Gold Project in Ghana, effective June 23, 2026.
- Base case outlines a conventional open-pit operation with milling and carbon-in-leach processing at 5.5 million tonnes per annum using contract mining.
- Study relies on a March 18, 2026 mineral resource estimate based on drilling through Oct. 6, 2025.
- More than 50,000 meters of additional drilling is excluded; ongoing 80,000-meter program targets higher-grade depth extensions beyond current pit limits.
- 2026 drilling results are slated for inclusion in future resource and reserve updates, with follow-on economic studies.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Bitcoin ETF inflows hit $3.8B in strongest three-week stretch of 2026

The Most Critical Date for the Bullish Cryptocurrency Bill Clarity Act Has Been Set
BPPB posts 1H 2026 net profit of EUR 23.7 million
Valued at 2 trillion! Anthropic may become the largest IPO in history, roadshow starts in October, listing before the midterm elections in November
According to sources familiar with the matter, Anthropic is expected to begin its IPO roadshow as early as mid-October and complete its listing just a few days before the U.S. midterm elections in November.