Zentek pegs Albany graphite project after-tax NPV at US$3.85 billion in new PEA
Reuters2026/08/10 12:11- Zentek released a new PEA for the Albany Graphite Project, modeling an integrated mine-to-purification operation targeting ultra-high-purity graphite markets.
- After-tax NPV at a 5% discount rate: USD 3.85 billion; after-tax IRR: 27.4%; discounted payback: 4.4 years; mine life: 30 years.
- Estimated initial capital: USD 817 million; sustaining capital: USD 1.16 billion; life-of-mine operating cost: USD 6.65 billion.
- Model assumes 30,000 tonnes of finished graphite products annually; weighted average realized product price: USD 23,485 per tonne; net annual revenue: USD 639.3 million.
- Bench-scale results cited purity of 99.9992% carbon without hydrofluoric acid; next work centers on purification scale-up, customer specifications, permitting.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
American Critical Minerals closes $2.54 million private placement at $0.2 per unit
Elnusa names Setyo Sapto Edi business development director, Linda Delina HR director
The 18-year S&P 100 inclusion will come to an end! Nike (NKE.US) urgently clarifies: It remains an S&P 500 constituent.
Nike is about to be removed from the S&P 100 Index, ending its nearly 18-year history as a component. In response to market questions regarding this development, Nike's investor relations team emphasized that this adjustment only pertains to the S&P 100 Index, and Nike remains a constituent of the S&P 500 Index.