KGHM completes Głogów II copper smelter overhaul early, restores production line
Bitget2026/10/02 11:47- KGHM completed a major maintenance outage at the Głogów II copper smelter ahead of schedule, restoring full operations.
- The outage halted the flash furnace line on June 28, then shut the electric furnace the next day.
- Work covered the full production line, with spending described as several hundred million zlotys.
- Commissioning restarted concentrate smelting on Sept. 16, 2026; electric furnace work finished on Sept. 30, ending the outage.
- The overhaul extends the interval between major maintenance outages to five years from four, supporting higher reliability and lower smelting costs.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Besent “Extinguishes Fire”: Rising US Treasury yields are a global phenomenon, dismisses concerns over AI bubble
U.S. Treasury Secretary Janet Yellen defended the rise in U.S. Treasury yields, stating that this increase is a global phenomenon rather than unique to the United States, and does not warrant excessive concern. She partially attributed inflationary pressures to higher oil prices caused by the Iran conflict, and expects the energy shock to subside as hostilities ease. Yellen refuted the notion of an AI bubble, arguing that investments by major tech companies are grounded in solid business logic.
Bitcoin Crash Warning Goes Viral as X Post Flags Benner Cycle

"New High" WLD rises to $0.6177, reaching a nearly 3-month peak